Delhi Airport to Shut Runway 28/10 for 90 Days from June 15, 2025, for Main Upgrades
NEW DELHI, India, Could 14, 2025 – Delhi’s Indira Gandhi Worldwide Airport (IGIA), operated by Delhi Worldwide Airport Ltd (DIAL), will quickly shut Runway 28/10, considered one of its 4 runways, for 90 days beginning June 15, 2025, to bear important upgrades. The closure, aimed toward enhancing security and operational effectivity throughout Delhi’s foggy winter season, will contain upgrading the runway’s Instrument Touchdown System (ILS) to CAT III B requirements and lengthening its lighting system from 650 meters to 900 meters. This follows a failed try in April 2025, which was halted after 4 weeks as a consequence of extreme flight disruptions.
Key Particulars of the Closure and Upgrades
- Objective: The upgrades will allow safer landings in low-visibility circumstances, significantly throughout Delhi’s winter fog, by equipping each ends of Runway 28/10 (Dwarka and Vasant Vihar sides) with CAT III B ILS capabilities. The prolonged lighting system will additional help operational reliability.
- Impression on Operations: With Runway 28/10 closed, IGIA’s capability will drop from dealing with 90 flights per hour (with all 4 runways) to 31–32 arrivals per hour underneath easterly winds, and as much as 42 underneath westerly winds. This discount, coupled with the airport’s typical 1,400 each day flights, is prone to trigger delays and cancellations.
- Earlier Try: An earlier closure on April 8, 2025, was deserted by April 21 as a consequence of poor planning, unseasonal easterly winds, and thunderstorms, which lowered arrival capability and led to 200–250 each day flight delays. The runway reopened on Could 6 after minimal progress on upgrades.
- Why June 15?: The June-to-September window coincides with a leaner journey interval because of the vacation season and a seasonal shift to westerly winds, which permits higher use of the remaining runways (09/27, 11R/29L, 11L/29R). This timing goals to attenuate disruptions in comparison with the height summer time journey interval in April.
Stakeholder Preparations
Civil Aviation Minister Ram Mohan Naidu convened a high-level assembly on Could 13, 2025, with representatives from all Indian airways, the Airports Authority of India (AAI), the Directorate Common of Civil Aviation (DGCA), and DIAL CEO Videh Kumar Jaipuriar. The minister directed airways to:
- Plan flight cancellations upfront to keep away from the chaos seen in April.
- Suggest measures to attenuate passenger inconvenience, equivalent to rescheduling flights to off-peak hours.
- Coordinate with air site visitors management (ATC) to optimize using the three operational runways.
DIAL has emphasised collaboration with stakeholders to make sure smoother operations, stating, “We’re working diligently with airways and all stakeholders to minimise any inconvenience.” The AAI will proceed ILS set up work off-runway (e.g., localizer and glideslope parts), which doesn’t intervene with flight actions.
Traveler Advisory
- Examine Flight Standing: Passengers are suggested to watch flight updates through airline apps or web sites, as delays are anticipated, significantly throughout peak hours.
- Plan Forward: Ebook flights early, enable further time for journey, and ensure schedules with airways to mitigate disruptions.
- Terminal Shifts: Word that Terminal 2 is closed till September 2025 for refurbishment, with its 45,000 each day passengers redirected to Terminal 1, growing congestion.
Context and Significance
Runway 28/10, the airport’s oldest, constructed by the British throughout World Battle II, is crucial for IGIA, one of many world’s busiest airports, dealing with important site visitors alongside newer runways (11R/29L, 11L/29R, 09/27). The CAT III B improve is important to cut back weather-related delays, as seen within the 2005 winter when fog induced document disruptions. The April fiasco uncovered gaps in India’s aviation ecosystem, significantly the shortage of a regulatory mechanism to implement flight reductions throughout infrastructure work, prompting Naidu’s proactive method.
Social media sentiment on X displays cautious optimism, with posts like @TheUrbanAcres noting airways’ preparations to attenuate disruptions, although customers like @Ghaziabad365 warn of potential “90 days of chaos” if planning falters. The upgrades, anticipated to be accomplished by September 15, 2025, goal to make IGIA extra resilient to winter fog, enhancing security and effectivity for hundreds of thousands of passengers.
Sources: India Right now, Instances of India, Hindustan Instances, News18, Livemint, posts on X